In my last post I made a remark about how our Lake Shelbyville trip was a much needed mini-vacation, and here's why! 

My last update on Dan and Theresa's shouse showed that the insulation was up and the ceilings in the garage and house portion were hung. Since then, the roof was completed and the drywall in the house portion was put up.

Fast forward to last week. On the third of July, Dan, Theresa, Eric, my mom, and I primed the walls and ceilings in the house portion (Thank you mom for all your help!!). The morning of the fourth, we gave the ceilings one coat of paint. Since then, the walls and ceiling have all had two coats of paint (thanks Charlotte for your help on Monday!), the front door is in, the floors are stained, and the majority of the siding is up. 



Talk about a productive week! Good thing too, since we have to be moved in in a little over a month!
 